ComplyChat

Your approved staff channel Just a mobile number. No IT account.

Try the apps free

Guide · Schools

Procurement Act 2023 for schools and academy trusts: thresholds, notices and the records to keep

The Procurement Act 2023 applies to a maintained school or academy trust in England when a contract's estimated value, including VAT, is at or above a threshold in Schedule 1 to the Act: since 1 January 2026, £207,720 for goods and services, £663,540 for light touch services such as school catering, and £5,193,000 for works.

By ComplyChatUpdated 20 minute read

ComplyChat is staff messaging for schools, charities and care. Everyone joins with a UK mobile number – no IT account and nothing to install – and paid plans meet your retention schedules within your own Microsoft 365 subscription. See how it works

On a grey winter afternoon in a modular cabin that serves as a multi-academy trust's estates office at the edge of a secondary school car park, three members of a tender evaluation panel – the trust's procurement lead, a woman in her fifties in a wool jumper, a school business manager in his thirties with a lanyard, and a head of facilities in a fleece – sit at three separate desks spaced apart, each reading a thick ring-bound bid with a pencil in hand, the pages turned away so no text can be read, a wall heater glowing under the window and parked cars blurred outside

Above those figures the Act requires notices on the Find a Tender service, a conflicts assessment prepared before the tender notice, and records that explain each material decision and keep every communication with a supplier about the award before the contract is entered into, held for at least three years. Below them, the Act's rules for below-threshold contracts do not apply to a school at all, and the school's own financial rules, its local authority's rules or the Academy Trust Handbook govern instead. This guide is for the school business manager, trust chief financial officer, procurement lead, headteacher or governor about to let a contract near the threshold, as the rules stand on 17 November 2026.

01

When the Act applies to a school, and the thresholds from 1 January 2026

The Procurement Act 2023 applies to a school when it awards a public contract, which section 3 of the Procurement Act 2023 defines as a contract for the supply of goods, services or works to a contracting authority that “has an estimated value of not less than the threshold amount for the type of contract” and is not an exempted contract. The Act received Royal Assent on 26 October 2023, and its main provisions came into force on 24 February 2025 under the Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 (S.I. 2024/716). The Department for Education's How to reduce procurement risk: good practice guide for academy trusts (15 July 2026) puts it plainly for trusts: “Academy trusts are contracting authorities and are responsible for managing public money when they award contracts under the Procurement Act 2023”, and the Act “generally applies to procurements which started on or after 24 February 2025.”

The Act names schools. Section 123 of the Procurement Act 2023 defines “school” to include “the governing body of a maintained school” and the proprietor of an Academy, as well as the proprietor of a non-maintained special school approved under section 342 of the Education Act 1996; and “a reference to a contract awarded by a school includes a reference to a contract awarded wholly for the purposes of supplying goods, services or works to a pupil referral unit.” The Act does not list schools as contracting authorities in terms. On our reading a school is one because section 2 defines a public authority as a person “wholly or mainly funded out of public funds, or subject to public authority oversight” that “does not operate on a commercial basis”, and the Act's own exceptions for “a contract awarded by a school” (set out below) assume as much.

The three thresholds that matter to a school, from Schedule 1 to the Procurement Act 2023 as amended from 1 January 2026:

  • £207,720 for a contract for goods or services (Schedule 1's row for a “sub-central government authority”, which means any contracting authority that is not a central government authority listed in Schedule 2 to the Procurement Regulations 2024; no school or academy trust in England is on that list).
  • £663,540 for a light touch contract (unchanged: it was the same figure when the Act started in February 2025).
  • £5,193,000 for a works contract, such as a building project.

Each threshold is compared with the contract's estimated value including VAT. Section 123(2) says “a reference to an amount payable or paid … under a contract includes a reference to any amount referable to VAT”, and the Cabinet Office's Guidance: Thresholds heads its table “Thresholds (including VAT): 1 January 2026 to 31 December 2027”. A £180,000 contract for standard-rated services is a £216,000 contract for this purpose once VAT is added, and over the threshold.

The figures changed on 1 January 2026 under the Procurement Act 2023 (Threshold Amounts) (Amendment) Regulations 2025 (S.I. 2025/1200). Before then the goods and services figure was £214,904 and the works figure £5,372,609; a page still quoting either is out of date, not describing another category. Regulation 3(1) keeps the old amounts for a procurement already under way: “Nothing in these Regulations affects any procurement commenced before the day on which these Regulations come into force”, which includes one whose tender notice or transparency notice had been published. The Cabinet Office's PPN 023: 2026 Threshold Amounts explains that the figures are revised every two years, and that the light touch threshold is not part of that cycle.

Not everything a school buys today runs under the Act. Regulation 5 of S.I. 2024/716 keeps the Public Contracts Regulations 2015 in place where, before 24 February 2025, a contracting authority had awarded the contract, concluded the framework agreement or established the dynamic purchasing system, among other cases, and in those cases “the Act does not apply”. The DfE's test for a trust buying from a framework: “If the procurement establishing the framework contract started before 24 February 2025, then Public Contract Regulations 2015 will apply. If it was after, the Procurement Act will apply.”

This guide covers England: Scottish devolved authorities are outside the Act (section 2(5)), and the DfE's guidance and the Academy Trust Handbook apply in England.

02

Valuing a contract: extension options, aggregation and light touch services

Whether the Act applies turns on the estimate. Under Schedule 3 to the Procurement Act 2023, paragraph 1(1), “A contracting authority must estimate the value of a contract as the maximum amount it could expect to pay under the contract including, where applicable, amounts already paid.” Paragraph 1(2) brings in “amounts that would be payable if an option in the contract to extend or renew the term of the contract were exercised”, and options to buy more. A three-year catering contract with an option to extend for two more years is valued over five years, VAT included.

Splitting a requirement does not take it under the threshold. Paragraph 4 of Schedule 3 applies where “the goods, services or works to be supplied under the contracts could reasonably be supplied under a single contract”: the authority “must estimate the value of each of the contracts as including the value of all of the contracts, unless the authority has good reasons not to do so.” Section 4(3) adds that a contracting authority “must not exercise a discretion in connection with estimating the value of a contract with a view to securing that any requirement of this Act does not apply in relation to the contract.” For trusts, the DfE's good practice guide asks you to “review repeated or recurring spend on similar goods or services across the whole trust” and to “recognise the trust as the contracting authority for the purposes of assessing contract spend on behalf of its schools, even where a scheme of delegation applies”.

A light touch contract is “a contract wholly or mainly for the supply of services of a kind specified in regulations” (section 9(1)). The services are listed by CPV code in Schedule 1 to the Procurement Regulations 2024 (S.I. 2024/692), and the list includes several that schools buy:

  • 55523100 School-meal services and 55524000 School catering services, with 55520000 Catering services and 55510000 Canteen services.
  • 80000000 Education and training services, with primary, pre-school and secondary education services beneath it.
  • 79620000 Supply services of personnel including temporary staff.

Building cleaning is not on the list, so a cleaning contract is an ordinary services contract with a £207,720 threshold. The classification depends on what the contract is wholly or mainly for; where a contract mixes services, check the codes in the Schedule rather than the contract title.

For a light touch contract the Act is lighter in ways a school will notice: the threshold is £663,540; the contract details notice is due within 120 days rather than 30 (section 53(1)(a)); there is no mandatory standstill (section 51(3)(f)); and the contract change notice (section 75(6)(b)), the key performance indicator duty (section 52(6)(d)) and the notice of a supplier's breach or poor performance (section 71(6)) do not apply.

03

What does not apply to schools, and what governs below the threshold

Several parts of the Act are switched off for schools by name. Each uses the defined word “school”, so each covers a maintained school's governing body as much as an academy trust:

  • Below-threshold contracts. Part 6 of the Act, on regulated below-threshold contracts, does not apply to procurement “by a school” (section 84(2)(a)). A school does not publish below-threshold tender notices under the Act.
  • Thirty-day payment terms. The payment terms implied into public contracts by section 68 do not apply to “a contract awarded by a school” (section 68(1)(c)), nor to sub-contracts under one (section 73(6)(c)).
  • Payment reporting. Payments compliance notices (section 69(6)(c)) and the information about payments over £30,000 (section 70(4)(c)) are not required of a school.

The DfE's good practice guide adds a practical caution for trusts: “Thirty day payment terms are not mandatory for schools, but they may still apply in practice. This is particularly true when you use a framework or dynamic market where the terms have already been set in the contract itself.”

Below the thresholds the Act does not govern the purchase, but the school's own rules do. The DfE's Buying procedures and procurement law for schools says “How you buy for your school depends on the amount you’re spending” and gives its own bands, which are guidance rather than law: low is under £10,000, medium is £10,000 to £40,000, and high is over £40,000. Its Find the right route to buy page says “Follow your school’s procurement rules. You can get these from your school or your local authority.” It is still worth recording value for money, the delegation limits applied and the competition run, even where the Act's record-keeping duty does not reach.

For academy trusts: the Academy Trust Handbook 2026

The Academy trust handbook 2026, effective from 1 October 2026, carries the procurement “musts” for trusts. Paragraph 2.25: the trust must ensure that “a competitive procurement procedure is in place and incorporated into the trust’s financial framework”, that “procurement rules and thresholds in the Procurement Act 2023 and its associated regulations are followed” and that the “Find a Tender service is used”. Paragraph 2.27: “Trusts must consider DfE opportunities when making purchasing decisions for goods and services and record their decision-making.”

Three paragraphs name particular contracts: supply staffing through the Government Commercial Agency framework “unless they have an alternative compliant agreement with rates which do not exceed those available through the framework” (2.28); the DfE's Energy for Schools service or a DfE approved energy deal “unless an alternative agreement of equivalent value for money has been sourced”, which “will apply when your energy contracts are renewed” (2.29); and management information system contracts under the DfE's MIS framework “as soon as practicable after its launch (planned for September 2027)” (2.30). Paragraphs 2.29 and 2.30 were clarified in September and October 2026. The Academy Trust Handbook guide covers the rest of the Handbook.

04

The notices on Find a Tender, in order, and when each is due

Every notice goes on the central digital platform, the Find a Tender service. In the order a school meets them, for a contract over the threshold:

  1. Planned procurement notice: optional, before the tender notice (section 15).
  2. Preliminary market engagement notice: if the school talks to the market before tendering, it must publish this before the tender notice or “provide reasons for not doing so in the tender notice” (section 17(1)).
  3. Tender notice, which starts an open procedure or a competitive flexible procedure (section 21); or, for a direct award where a direct award justification applies under section 41, a transparency notice before the contract is awarded (section 44). The conflicts assessment must exist before either is published (section 05 below).
  4. Assessment summaries to each supplier that submitted an assessed tender, then the contract award notice, which must be published “Before entering into a public contract” (section 50).
  5. Standstill. The mandatory standstill is “the period of eight working days beginning with the day on which a contract award notice is published” (section 51(2)), and a working day excludes weekends and a bank holiday in any part of the United Kingdom (section 123(1)). It does not apply to a light touch contract, a contract awarded in accordance with a framework or by reference to a dynamic market, or an urgent direct award (section 51(3)). For those, any standstill is voluntary, but if the contract award notice provides for one it may not be less than eight working days (section 51(4) and (5)).
  6. Contract details notice: “before the end of the period of 30 days beginning with the day on which the contract is entered into”, or 120 days for a light touch contract (section 53(1)). The clock runs from the day the contract is entered into, not from the award decision.
  7. Contract change notice before modifying the contract, unless the change moves its value by 10 per cent or less (goods and services) or 15 per cent or less (works), or its term by 10 per cent or less of the maximum term; small changes that could reasonably have been made together are added up. It does not apply to a light touch contract (section 75).
  8. Notice of a supplier's breach or poor performance: within 30 days, where a supplier's breach of a public contract results in termination or partial termination, the award of damages or a settlement agreement, or where a supplier given proper opportunity to improve unsatisfactory performance has failed to do so (section 71(3) to (5)). Not for a light touch contract.
  9. Contract termination notice: “Before the end of the period of 30 days beginning with the day on which a public contract is terminated” (section 80(1)), and termination includes expiry, so a contract that simply runs its course still needs one.
  10. Procurement termination notice: if, after publishing a tender or transparency notice, the school decides not to award, it must give notice “As soon as reasonably practicable after making the decision” (section 55).

For a call-off under a framework, the Cabinet Office's guidance on contract award notices and standstill says that “in the case of call-off contracts, assessment summaries and standstill periods are not required”, but the contract award notice still comes first (section 50(1)), and its guidance on contract details notices confirms that the contract details notice is needed for “call-off contracts that are public contracts”.

Three duties start only at sizes few schools reach. Before entering into a public contract with an estimated value of more than £5 million, a contracting authority must set and publish at least three key performance indicators, unless it considers performance could not appropriately be assessed that way, and assess performance at least once every twelve months (section 52 and section 71(2)); not for frameworks or light touch contracts. A contract over £5 million must also be published in full within 90 days, or 180 days for light touch (section 53(3)). A pipeline notice is needed only by an authority that expects to pay more than £100 million under relevant contracts in the coming financial year (section 93).

The DfE's July 2026 good practice guide counts the standstill as the Act does: “At least 8 working days must pass beginning from the day you publish the contract award notice.” Where an older DfE page gives calendar days, or counts the contract details notice from the award, follow sections 51 and 53.

05

The conflicts assessment: before the tender notice, and kept under review

A school must “take all reasonable steps to identify, and keep under review” conflicts and potential conflicts of interest in a covered procurement (section 81(1)), and the duty reaches beyond the evaluation panel: “A person who influences a decision made by or on behalf of a contracting authority in relation to a covered procurement is to be treated as acting in relation to the procurement” (section 81(3)). Section 82 then requires all reasonable steps to ensure a conflict does not put a supplier at an unfair advantage or disadvantage; where an unfair advantage cannot be avoided, or the supplier will not take the steps needed, the supplier must be treated as excluded from that award.

The assessment itself is a document with a deadline. Section 83(1): “Before publishing a tender or transparency notice in relation to a covered procurement, a contracting authority must prepare a conflicts assessment in relation to the procurement.” It sets out the conflicts identified and the steps taken to mitigate them (section 83(3)) and, where circumstances might lead a reasonable person to believe wrongly that there is a conflict, the steps taken to show there is none (section 83(4)). The school must “keep any conflicts assessment under review” and “revise the assessment as necessary” (section 83(5)), and confirm that it has been prepared and revised when it publishes a tender, transparency, dynamic market, contract details or contract change notice (section 83(8)); the contract award notice is not on that list. The Act does not require the assessment itself to be published.

The DfE's good practice guide is direct: “A conflict assessment is legally required for every procurement covered by the Procurement Act.” It explains why the register of interests is not the answer: “An annual declaration of interests is not enough on its own because conflicts:”

  • can arise at any stage
  • may relate to specific procurement requirements
  • may involve individuals who are not required to complete your trust’s annual declaration

It also notes that “conflict assessments normally contain personal data”, so the trust's privacy notices and records of processing should cover them. Where the supplier is a related party of an academy trust, the Handbook's related party rules apply as well as the Act; related party transactions in academy trusts sets those out, and the conflict of interest policy guide covers the general policy.

On an overcast July morning in the rear service yard behind an English secondary school kitchen, the school business manager, a woman in her forties in a striped summer shirt, shows two catering companies' representatives in plain dark polo shirts round on a site visit before a tender, one of them measuring the width of the open roller-shutter delivery door with a tape measure while the other looks up at the stainless steel extraction flue on the brick wall, plain grey wheeled bins and a stack of empty bread crates beside them, no lettering or logos anywhere
06

The record section 98 requires, and what the DfE says the file holds

Section 98 of the Procurement Act 2023 sets two record-keeping duties for every public contract. The first: “A contracting authority must keep such records as the authority considers sufficient to explain a material decision made for the purpose of awarding or entering into a public contract.” A decision is material if the Act requires the authority to make it, or to publish or provide a notice, document or other information about it (section 98(2)).

The second is about suppliers: “A contracting authority must keep records of any communication between the authority and a supplier” made in relation to the award or entry into of a public contract and before the contract is entered into (section 98(3)). It says any communication, not formal correspondence, so a clarification by phone, a word at a site visit and a message to a member of staff are all within it.

Both records must be kept until the school gives notice that it will not award the contract, or until “the end of the period of three years beginning with the day on which the contract is entered into or, if the contract is awarded but not entered into, awarded” (section 98(4)). Three years is a floor, not a schedule: section 98(6) leaves in place any other obligation to keep records “including for a longer period”, and the DfE tells trusts: “You must keep records for as long as your own retention policy requires. That must be no less than the minimum period required by the Procurement Act.” The data retention policy guide covers writing that policy.

Two limits are worth knowing. The duty attaches to a public contract, so it does not reach a purchase below the threshold. And the supplier communication duty stops when the contract is entered into; what follows belongs to contract management.

The DfE's good practice guide for trusts goes further than the Act. It says “You must keep: all communications between the trust and suppliers that relate to the award of a contract” and “any document that explains a material decision taken during the procurement”, and lists what the records may include:

  • planning documents, including how national government priorities were considered
  • any market engagement activity and findings
  • conflict of interest assessments
  • assessments of supplier exclusions
  • evaluation notes and moderation records
  • assessment summaries
  • the final contract
  • any correspondence relating to these documents

Where a local authority, a framework provider or a buying organisation runs part of a school's procurement, agree before the tender notice who keeps which part of the file. The same file is what a request under the Freedom of Information Act reaches; freedom of information in schools covers the time limits.

07

Where ComplyChat fits, and where it does not

ComplyChat is not an e-tendering system or a contract management tool. It publishes nothing to Find a Tender, does not hold bids or run evaluations, and nothing about it makes a school or trust compliant with the Procurement Act 2023. Questions from bidders belong in the tender system or email: the DfE's Route 5: run a process compliant with the Procurement Act 2023 for high value purchases page recommends that you “ask suppliers to send questions through an e-tendering solution or by email” and “keep a log of the questions and answers you gave and share these with all suppliers”.

What it touches is narrower: the conversations around a procurement that happen in messages. A supplier's account manager who texts a business manager's own phone during a tender has made a communication that section 98(3) requires the school to keep, on a phone the school cannot search. The evaluators agreeing a moderated score in a staff group chat, or the head and the business manager deciding over a weekend whether to take up an extension option, are part of how a material decision was reached, and the DfE expects the file to explain it.

ComplyChat is designed to bring the staff side of those conversations into channels the school or trust runs. Staff are added by their mobile number, verified by SMS, so nobody needs an account on the school's systems; everyone added is told the channel is on the record and can object or leave; and messages are recorded on the server as they are sent. On paid plans, once the school's or trust's tenant is connected, they are kept under the retention schedules within its own Microsoft 365 subscription, where the procurement file can reach them. It replaces the staff group chat; it does not capture WhatsApp, and it is not where supplier clarifications should go.

A question for the next finance committee or board meeting: if a bidder challenged last year's largest contract, could you produce every message a supplier sent to a member of staff before it was signed?

08

Questions people ask

Does the Procurement Act 2023 apply to schools?

Yes, the Procurement Act 2023 applies to maintained schools and academy trusts in England for any contract whose estimated value, including VAT, is at or above the thresholds in Schedule 1; section 123 names the governing body of a maintained school and the proprietor of an Academy as a “school”. Below the thresholds Part 6 of the Act does not apply to procurement by a school, and the school's own procurement rules govern.

What are the procurement thresholds for schools in 2026?

From 1 January 2026 the thresholds are £207,720 for goods and services, £663,540 for light touch services such as school catering, and £5,193,000 for works, each measured against the contract's estimated value including VAT; the goods, services and works figures run to 31 December 2027. The £214,904 figure still found online was the goods and services threshold before 1 January 2026.

What is the new procedure introduced under the Procurement Act 2023?

The competitive flexible procedure, which sits beside the single-stage open procedure. In the DfE's words, “You can design your own procurement through a number of stages, using evaluation at each stage to restrict the number of bids”, provided the tender notice sets out how the process will be designed and carried out.

What are the latest updates to the Procurement Act 2023?

The thresholds changed on 1 January 2026 (S.I. 2025/1200). For academy trusts, the DfE published its good practice guide on reducing procurement risk on 15 July 2026, and the Academy Trust Handbook 2026 has applied since 1 October 2026. A new Part 5A, inserted for specified purposes from 6 January 2026 by the Employment Rights Act 2025, “provides for a Minister of the Crown, the Scottish Ministers and the Welsh Ministers to make provision for the protection of workers in relation to relevant outsourcing contracts” (section 83A(1)).

How long must a school keep procurement records?

For a contract over the threshold, at least three years beginning with the day the contract is entered into, or until the school gives notice that it will not award it (section 98(4) of the Procurement Act 2023). Longer retention duties elsewhere still apply (section 98(6)).

Do schools have to pay suppliers within 30 days under the Procurement Act?

No, not by force of the Act: the 30-day payment terms implied by section 68 do not apply to a contract awarded by a school, or to sub-contracts under one (section 73), and schools do not publish payments compliance notices or payment information. The DfE notes that 30-day terms may still apply in practice, for example through a framework's own terms.

09

Official guidance and your next step

The Procurement Act 2023 is on legislation.gov.uk, with the thresholds in Schedule 1 and the valuation rules in Schedule 3; the Cabinet Office's Guidance: Thresholds sets the 2026 figures out in tables, and the light touch services are listed in Schedule 1 to the Procurement Regulations 2024 (S.I. 2024/692). For schools, the DfE's Buying procedures and procurement law for schools explains the five routes to buy, with Route 5 for purchases over the threshold. For trusts, the DfE's How to reduce procurement risk: good practice guide for academy trusts (15 July 2026) is good practice rather than law, and says “You should not rely on it as legal or commercial advice”; the Academy trust handbook 2026 carries the binding “musts”. The DfE's Find the right route to buy page also says: “We recommend that you get legal advice if what you are buying is over, or near to the thresholds.” Quotations are from the pages named as read on 16 and 17 November 2026.

This guide covers maintained schools and academy trusts in England. It is not legal advice.

Then do one thing: take the next contract due for renewal – catering, cleaning, ICT or a building project – and write down its estimated value over the full term with every extension option, including VAT, whether it is light touch, and the date its contract details notice would fall due. If the figure is anywhere near £207,720 or £663,540, open the conflicts assessment and the procurement file now, before the tender notice.

Why we publish this

We build ComplyChat for the work conversations schools and trusts need to be able to find when a decision is questioned. Explore Free personal messaging, or compare the paid plans if your school or trust needs its conversations kept under the retention schedules within its own Microsoft 365 subscription.

Explore Free · How it works · Compare plans

Sources

Every document this guide quotes or links to, in the order it first cites them.

  1. Section 3 of the Procurement Act 2023 legislation.gov.uk
  2. The Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 (S.I. 2024/716) legislation.gov.uk
  3. How to reduce procurement risk: good practice guide for academy trusts gov.uk
  4. Section 123 of the Procurement Act 2023 legislation.gov.uk
  5. Section 2 legislation.gov.uk
  6. Schedule 1 to the Procurement Act 2023 legislation.gov.uk
  7. Schedule 2 to the Procurement Regulations 2024 legislation.gov.uk
  8. Guidance: Thresholds gov.uk
  9. The Procurement Act 2023 (Threshold Amounts) (Amendment) Regulations 2025 (S.I. 2025/1200) legislation.gov.uk
  10. PPN 023: 2026 Threshold Amounts gov.uk
  11. Schedule 3 to the Procurement Act 2023 legislation.gov.uk
  12. Section 4(3) legislation.gov.uk
  13. Section 9(1) legislation.gov.uk
  14. Schedule 1 to the Procurement Regulations 2024 (S.I. 2024/692) legislation.gov.uk
  15. Section 53(1)(a) legislation.gov.uk
  16. Section 51(3)(f) legislation.gov.uk
  17. Section 75(6)(b) legislation.gov.uk
  18. Section 52(6)(d) legislation.gov.uk
  19. Section 71(6) legislation.gov.uk
  20. Section 84(2)(a) legislation.gov.uk
  21. Section 68 legislation.gov.uk
  22. Section 73(6)(c) legislation.gov.uk
  23. Section 69(6)(c) legislation.gov.uk
  24. Section 70(4)(c) legislation.gov.uk
  25. Buying procedures and procurement law for schools gov.uk
  26. Find the right route to buy gov.uk
  27. Academy trust handbook 2026 gov.uk
  28. Section 15 legislation.gov.uk
  29. Section 17(1) legislation.gov.uk
  30. Section 21 legislation.gov.uk
  31. Section 41 legislation.gov.uk
  32. Section 44 legislation.gov.uk
  33. Section 50 legislation.gov.uk
  34. Section 80(1) legislation.gov.uk
  35. Section 55 legislation.gov.uk
  36. Guidance on contract award notices and standstill gov.uk
  37. Guidance on contract details notices gov.uk
  38. Section 93 legislation.gov.uk
  39. Section 81(1) legislation.gov.uk
  40. Section 82 legislation.gov.uk
  41. Section 83(1) legislation.gov.uk
  42. Section 98 of the Procurement Act 2023 legislation.gov.uk
  43. Route 5: run a process compliant with the Procurement Act 2023 for high value purchases gov.uk
  44. Section 83A(1) legislation.gov.uk
  45. Procurement Act 2023 legislation.gov.uk